Main Storage Tank Replacement at an Active Healthcare Facility
Facility Type
Regional Healthcare Facility
Location
Greater Toronto Area

Project Scope
Temporary fuel provisioning, tank removal coordination, new base pad, custom fabrication of protective bollards.
The Challenge
Underground tank nearing end of life requiring replacement with a double-wall aboveground unit.
In critical facilities, fuel system deficiencies pose an immediate risk to life-safety operations. Prolonged downtime during remediation is rarely an option, requiring precise planning and execution.
The Solution & Execution
Our team developed a comprehensive execution plan that prioritized maintaining backup power readiness while the new systems were installed.
- Detailed site assessment to verify routing and clearances
- Custom fabrication of required supports off-site
- Coordinated shutdown and transfer sequencing
- Final testing, commissioning and TSSA compliance documentation
Project Result
Seamless transition ensuring life-safety power remained continuously available throughout the project.
Services Used on This Project
Related Guides
Have a Similar Project?
Our team is ready to review your requirements, site constraints, and applicable compliance standards.
Discuss Your Project