fuel polishing
Comprehensive Fuel Polishing and Tank Remediation
Facility Type
University Campus
Location
Southern Ontario

Fig 1. Final installation showing clean steel fuel piping, supports, and containment, executed to TSSA standards.
Project Scope
Multi-stage fuel polishing, tank bottom extraction, biocide treatment.
The Challenge
Routine sampling indicated heavy microbial growth and water bottom in 20,000L backup tank.
In critical facilities, fuel system deficiencies pose an immediate risk to life-safety operations. Prolonged downtime during remediation is rarely an option, requiring precise planning and execution.
The Solution & Execution
Our team developed a comprehensive execution plan that prioritized maintaining backup power readiness while the new systems were installed.
- Detailed site assessment to verify routing and clearances
- Custom fabrication of required supports off-site
- Coordinated shutdown and transfer sequencing
- Final testing, commissioning and TSSA compliance documentation
Project Result
Fuel restored to clear and bright condition, avoiding costly complete replacement.